To:                EWPATAS (Enterprise Wide Positive Attendance Tracking and Attendance System) PTO members

 

From:            Co Ho, Project Leader            

                    

Date:             04/25/01

 

Subject:         Status Report

 

 

As of today, the progress statistic of the EWPATAS system development is as followed:

 

·        Tracking subsystem: We are at 78% completion state, 1.5 week behind schedule.  We are estimating that release 5.5 will be released by 5/21/01.  The 6.0 release is having a tentative release on 6/8/01, plus or minus 8 days.  Please note that as of release 5.0, the system is ready for standalone beta testing.  Release 5.5 will support network routing and release 6.0 will support near-real time DB validation.

 

·        Accounting subsystem: We are at 67% completion.  Work on new Banner DB integration is scheduled to run parallel with the 6.0 release of the tracking system in late May.  Target completion for DB integration for accounting subsystem is in July.

 

·        Web front end subsystem:  We are at 23% completion with the kernel layer of J2EE architecture in place.  We do not schedule any intensive work on this until late June due to human resource constraints.

 

Overall, we are confident that the system will be ready for wide beta testing during Summer School and for production by Fall Semester.